Faq's
29 de April de 2018
29 de April de 2018
31-03-2015.- Through their affiliate in Uruguay, HASFOY SA, ENERGES has successfully completed the Electrical Assembly work for the 65 MW “La Jacinta” photovoltaic plant, where they […]
29 de April de 2018
29 de April de 2018
01-08-2015.- ENERGES, through their affiliate in Uruguay HAFOY SA, has started the Electrical Assembly work for the 50 MW Kiyú Wind Farm, as the electrical subcontractor […]
29 de April de 2018
29 de April de 2018
01-10-2015.- Energes has started work on the construction of a 1.89 MW photovoltaic power plant in Alcolea del Río (Seville). The project developer is the nonprofit […]
29 de April de 2018
29 de April de 2018
Energes finished work on the 2 MW Vallehermoso II power plant in December. The power plant will produce 3,240 MWh per year, enough to supply electricity […]
29 de April de 2018
29 de April de 2018
The 64 MW photovoltaic plant of La Jacinta in Uruguay recently started up following completion of the construction. ENERGES has carried out the Electrical Assembly of […]
29 de April de 2018
29 de April de 2018
On 1 February, the regional association “GRAN VEGA”, represented by Juan Carlos Expósito and Carlos López as the President and Vice-president respectively, and ENERGES, represented […]
29 de April de 2018
29 de April de 2018
Industrial Self-Consumption may be viable if we are able to match the solar generation curve with the load curve, in spite of the ‘sun tax’ […]
31 de May de 2018
31 de May de 2018
The photovoltaic installation “La Matallana” of 2 MW has achieved the Commissioning. Only the connection to the grid is pending to start operating.
13 de June de 2019
13 de June de 2019
The 100kW Industrial Self-consumption photovoltaic installation of “Torres y Ribelles” is working. After 12 days of execution of the works and some more processing with Industry […]